EPS@ISEP | The European Project Semester (EPS) at ISEP

Logbook

Weekly Report

1st Week Report (Calendar Week (CW) 9)

Introduction into the European Project Semester, courses, teams and proposal of projects. Discussion within the group and with coaches/professors, introduction into the workplaces and final choice of project.

2nd Week Report (CW 10)

First research was done on biological inspirations and technological state of the art to prepare a future concept.

3rd Week Report (CW 11)

The tasks necessary to achieve progress in the project were defined, allocated and scheduled. Further research was done on the biological inspiration and state of the art. Ideas for an effective marketing concept were collected.

4th Week Report (CW 12)

The market concept was chosen and the product development initiated.

5th Week Report (CW 13)

While the product was under development it was worked on the chapters on Marketing, Ethics & Deontology and Sustainability for the Report.

6th Week Report (CW 14)

To finish the list of materials the emphasis was put on developing the product. Also the Interim Report was finished and handed in.

7th Week Report (CW 15)

The product development was roughly finished and the interim presentation prepared and held.

8th & 9th Week Report (CW 16 & 17)

Easter Vacation

10th Week Report (CW 18)

Work on final report

11th Week Report (CW 19)

Detailed product development, continue deliverables

12th Week Report (CW 20)

Finish electronic circuit, Finish Marketing Plan

13th Week Report (CW 21)

Work on final report

14th Week Report (CW 22)

Finish final details for 3D printable parts, Finish Project Management chapter

Meetings

1st Meeting (2014-02-27)

Agenda:

  1. Presentation
  2. Modus operandi
  3. Project proposals
  4. Electronic Logbook

Minute:

First EPS meeting, including introduction of the EPS supervisors, teams, further proceeding and detailed presentation of the electable projects.

2nd Meeting (2014-03-06)

Agenda:

  1. OBJECTIVE
    • Target market, final costumer?
    • Is there a specific shape, dimension and movement of the fish required?
    • Which functions is the remote control expected to have?
    • Maximum production costs?
  2. TECHNOLOGICAL DEVELOPMENT
    • What are the existing components that we are able/supposed to use?
    • Can you help us to get information on technical (mechanical/electrical/material) features of existing robotic fish? Copyrights?
    • Are we expected to build the entire final prototype?
  3. BUDGET
    • Is the entire budget for buying components for the prototype?
    • Does the early deadline for list of materials mean that we have to be done with the product development by then? Can we buy more components later on?
  4. GENERAL
    • Can we plan meetings out of schedule to discuss important questions?

Minute:

  1. Manuel Silva was declared advisor for this project.
  2. The target customer is to be determined as part of the marketing concept.
  3. Functions, shape and means of controlling are to be determined by the team (recommendation by coaches: big enough to fit in necessary components and create enough buoyancy).
  4. Discussion on usage of existing components was postponed.
  5. A meeting with advisor was set up to be provided with further information on state of the art.
  6. There will be no problems concerning copyrights as long as the team creates an original design, team has to be aware of existing patents.
  7. A prototype is to be built.
  8. To use the budget the components can only be bought via ISEP (deadline is obligatory).

3rd Meeting (2014-03-13)

Agenda:

  1. PRESENTATION OF RESEARCH RESULTS
    • Biological inspiration
    • Technological state of the art
  2. QUESTIONS ON FURTHER PROCEEDINGS
    • What is the more important task: create a working marketing concept or implement a robot that can fulfill “basic fish movements”?
    • How specified should the list of materials be?
    • What kind of machines does ISEP have to cut materials etc. or do we have to buy semi-finished products?

Minute:

  1. The research results were presented.
  2. The high degree of maneuverability and effective stationkeeping due to streamline shape of fish and combination of oscillating and undulating movements were stated the most important biological inspirations.
  3. The engineering design should strive for simplicity to produce feasibility and low power consumption. The usage of a Arduino platform may help reach that goal.
  4. An effective marketing concept has to be developed for the product. Not all of the future product features need to be implemented in the first prototype. Single features (such as up/down movement) can be selected to be tested in the prototype.
  5. Concrete products of (local) companies have to be specified for the list of materials.
  6. ISEP facilities include machines to cut metal (esp. aluminium) and plastic materials. There is also a 3D-Printer. Technical drawings are required to have any materials processed. Costs are expected to be lower this way than for buying semi-finished products.

4th Meeting (2014-03-20)

Agenda:

  1. Presentation of Marketing Concept
    • Main Idea
    • Possible target market ideas
  2. Questions on defining the target market
    • Is an entire market analysis necessary?
    • Should we put more weight on the technical complexity necessary to create a product that meets the target´s needs?
  3. Presentation and discussion of Technical Solution
    • Possible mechanical architecture of fish
    • Possible functions of prototype
  4. Presentation and discussion of action plan for the upcoming week (displayed in the following)
    1. Choose target market
    2. Define mechanical architecture of fish (maximum functions ↔ minimum complexity)
    3. Choose type of mechanical and electrical components
    4. Developing a shell/hull (criteria: space for components, outweighed buoyancy, waterproof, little drag resistance)
    5. Choose material for shell/hull

Minute:

  1. Positive feedback was received on the the principal marketing idea. The target market is for us to choose based on market research. The more, the better.
  2. To minimize complexity a two-staged project structure is proposed:
    1. Implementation of basic behavior into prototype (little amount of properly working functionalities).
    2. Generation of more complex behavior by altering controlling algorithms. (if possible within time available)
  3. Possible mechanical architectures of the robot were discussed regarding performance and feasibility. More research has to be done to select the best of the three remaining options. Manuel Silva and Fernando Ferreira can be consulted for further advice on specific problems.
  4. The prototype should have the functionality to move straight, left/right and up/down. The team has to decide on the remote controllability. Fins of different shapes and sizes can be connected to the motors to experiment on the physical effects. It was also discussed if masses may be integrated in the hull at different locations to change the overall weight and center of gravity. The decision will be made during the technical development process.
  5. The proposed action plan met approval. The following advices were given to support the technical development:
    • A top-down method should be used to identify all necessary components and produce a more and more detailed specification for them.
    • Suitable mechanisms and off-the-shelf-products can reduce the system´s complexity.
    • Actuators: Servomotors may be used for pectoral fins (if existing). The tail fin producing thrust should be actuated by a motor with uninterrupted spin (not servo) to minimize power consumption and material abrasion (hint: how are swipers for windshields of cars actuated?). (comparison criterion: power in-/output, price, weight, dimensions)
    • Controller: microprocessors by Arduino, TI or Launchpad may be suitable. Raspberry Pi is to complex. (comparison criterion: power consumption, price, weight, dimensions)
    • Battery (comparison criterion: power autonomy, price, weight, dimensions)
  6. General propositions:
    • The subchapter “Requirements” of chapter “Introduction” of the report should be defined by the team. Functional tests for every proposed feature of the prototype should be introduced in the following chapter.
    • Requirement of 12hrs power autonomy may be modified if not realizable.
    • The first week of April may also be used to define the list of material. (deadline not mandatory)

5th Meeting (2014-03-28)

Agenda:

  1. Presentation of development status
  2. Questions in order to do list of materials concerning…
    • mechanical archtitecture to steer left/right
    • mechanical structure of back fin
    • calculation of torque of back fin
    • remote control + receiver
    • microprocessor: arduino uno r3 or arduino pro mini?
    • batteries: lithium?
    • way of changing overall mass and its center: water or weight
    • waterproof shell
    • support structure for components
    • set up a meeting to see facilities where we will build prototype

Minute:

  1. concerns were expressed about our idea to only steer with the pectoral fins: it would inevitably lead to a rotational motion around the longitudinal axis and also work against the kinetic energy achieved by propelling the robot
  2. one motor can be used for both pectoral fins if they are supposed to have the same movement always, the shape of the fish and the orientation of rotational axis have to be considered in an approach like that
  3. concerns were expressed about the presented mechanical mechanism for the back fin because it would produce different angular velocities during one period and thus the fish runs the risk of swimming in circles only
  4. the first idea for the mechanisms does not have these problems but requires a lot of space and is harder to make waterproof
  5. Supervisor Fernando suggested another option to construct and actuate the back fin that met general approval
  6. for the back fin a motor of relatively high torque and less speed is useful
  7. to change the voltage a PWM is supposed to be a better solution than a potentiometer
  8. the two micro processors differ mainly in size, the mini requires an additional programming cable, there are advantages and disadvantages to both options, a choice has to be made dependent on the size of the fish
  9. also the choice of batteries is dependent on the size of the fish and the required weight to balance it (heavier and cheaper batteries may be used because the weight is needed anyways)
  10. the choice how to implement the ballast (water container or weights) is dependent on how much additional mass we want to add, a water tank only offers a limited capacity to add weight
  11. to make the hull waterproof our idea (put a “hat” on the main body separated by a rubber strap and tighten it with a belt around the entire body) was criticized because it requires high geometric accuracy; it was stated that sealing is easiest if there are simple geometries attached to each other because reaching accuracy is easier; it also has to be considered that we need to be able to access all components with this inspection opening

6th Meeting (2014-04-03)

Agenda:

  1. Presentation and discussion of the current design of the swimming robot and the list of materials
  2. Question concerning remote controlling unit

Minute:

  1. the principal design of the fish (static and dynamic parts) met approval
  2. it was advised to choose a larger pieces to connect the tail fins in order to secure enduring strength
  3. the topics watertightness and electrical components were discussed and further meetings with the supervisors Manuel and Fernando scheduled
  4. new possibilities to activate the body were introduced:
    • use of smart materials activated by applying voltage to them, the team can contact supervisor Cristina for further information
    • a belt can be put around the fish´s body (in a layer orthogonal to longitudinal axis) with several fins attached that rotate differently
  5. the presentation may be handed in on wednesday, 09th april

7th Meeting (2014-04-30)

Agenda:

  1. Questions concerning procurement
    • When do materials arrive?
    • Is there a place at ISEP to store the materials?
  2. Presentation of action plan for prototype implementation
    1. cut pipe
    2. (squeeze pipe)
    3. prepare drawings for 3D printing and machining
      • pipe caps
      • aluminum pieces for shaft opening
      • support for parts inside shell
    4. 3D printing
    5. machine plastics and aluminum
    6. build control unit
    7. cut fins
    8. attach fins to shafts
    9. assemble all parts
  3. Questions the implementation
    • Which tools are we allowed to use ourselves? Where and when?
    • Does the 3D printer work properly?
    • Who will do the 3D printing/machining (contact details, how long does it take?)

Minute:

  1. it cannot be stated when materials will arrive
  2. the EPS room will serve as work base and will be equipped with tools
  3. questions concerning 3D printing can be discussed with Fernando (required file format, time consumption)
  4. contact technicians at ISEP to schedule machining (shorthanded operation should be possible)
  5. transparent caps can be provided by Manuel (drawing required)
  6. it is suggested to use a mock-up of an empty hull for initial buoyancy tests before inserting electronics

8th Meeting (2014-05-07)

Agenda:

  1. What are the supervisors´ individual expectations towards the project and the team?
  2. Which of the following “services” should we already finish during the EPS semester?
    (alternative: hint that the team intents to do it in the future)
    • User´s manual
    • Safety instructions
    • Terms of warranty
    • Costs of usage and maintenance
  3. Where does a chapter on the final product fit best in the report?
  4. How can we calculate the final product costs?
  5. Should we include European standardized tests, e.g. CE, into our product development?

Minute:

  1. detailed technical drawings should be handed in as soon as possible
    • body (back fin segments, caps, etc.)
    • control circuit (use 123D Circuit; 123D Apps to simulate the control circuit!)
  2. supervisors shared their expectations
  3. Terms of warranty should be done according to EU standards (2 years)
  4. a user´s manual should be provided including safety instructions, also user´s videos for standard operations could be helpful
  5. inspiration on the product packaging was given (like a sardine can?)
  6. cost assessment
    • at least the costs of prototype development can be assessed (materials, design&development, production, labour cost)
    • ask marketing teacher about price drop down to final product
    • production quantity is probably required → find reliable measures of quantities of sale or create a scenario
    • product costs should preferably not exceed 40€ (in Manuel´s opinion)

9th Meeting (2014-05-15)

Agenda:

  1. when can we start working on the prototype? Are the materials here?
  2. present the newest design
  3. presentation of technical drawings
    • are the drawings detailed enough?
    • dimensions problems in some parts
  4. presentation of electronic circuits and quick overview of electronics

Minute:

  1. materials have not yet arrived
  2. technical drawings will be discussed in another meeting appointed with Manuel
  3. architecture of tail was discussed, especially methods to create a streamline surface, a solution is not yet found
  4. different materials to create the streamline were discussed, e.g. neoprene, mylar, dacron
  5. pins to connect tail segments should be made of stainless steel rather than plastics

10th Meeting (2014-05-22)

Agenda:

  1. Presentation of current Mechanical Design
  2. Questions about EPS Calendar:
    • Upload of final deliverables already at the 8th June??
    • Does the presentation also need to be done by then?
    • Do all team members need to be present at the final hand-in date (19th June)?
    • What is the “Resit Assessment” for?
  3. Questions about contact details of Supervisors (information collected for report)

Minute:

  1. whenever supervisors Manuel and Fernando give “green light” on designs, work in the workshop can start
  2. a better 3D printer (higher accuracy) was arranged, Fernando will forward the drawings
  3. discussion about required shape of shaft to propel the fish, this issue will have to be experimented on the prototype
  4. a spring, installed at the last segment of the tail fin, could maybe improve the tailmovement
  5. an appointment was set with Fernando to improve little details on the parts in order to make them printable
  6. the calendar on the wiki is right, google calendar had mistakes, the upload date is on 12th June
  7. presentation can be uploaded later, one day before presentation day
  8. contact data of professionals at ISEP can be found in ISEP Portal

11th Meeting (2014-05-28)

Agenda:

  1. Questions about list of material (concerning electrical parts)

Minute:

  1. materials have not yet arrived
  2. there are problems with the procurement of battery and 3D prating wire, supervisors will take of that
  3. 3D printing can start as soon as last technical details are discussed with Fernando and implemented into the 3D model
  4. the team has to buy some of the components itself, therefore some of the budget was made available for us
  5. Video and poster can be uploaded together with presentation on 18th June

12th Meeting (2014-06-05)

Agenda:

  1. Question about content of wiki

Activities

Start End Task Description Who
2014-02-27 Choice of project / all
2014-02-28 2014-03-05 Prepare EPS Meeting No.1 Research on status quo, prepare questions all
2014-03-06 2014-03-12 Planning and Research biological inspiration, state of the art, tasks and allocation, Gantt chart all
2014-03-16 2014-03-16 Research on biological inspiration visit at the aquarium (Estacao Litoral Da Aguda) Magdalena, Marcin
2014-03-17 2014-03-19 Marketing concept Brainstorm/Research/Discussion all
2014-03-20 product development, report the architecture was developed and components chosen, the report was prepared for the interim assessment all
2014-05-12 2014-06-03 Finish technical product development prepare the 3D model so that parts can be printed, discuss details with Fernando Marcin
2014-05-19 2014-05-31 Finish part of Project Management for Report elaborate all issues and send file to teacher by 31th May Magda
2014-05-30 2014-06-02 Project Management Presentation Prepare a commercial presentation (format based on the interim assessment) Alicia
Print/export
QR Code
QR Code log (generated for current page)