| log [2014/06/02 11:04] – team1 | log [2022/11/03 10:45] (current) – external edit 127.0.0.1 | ||
|---|---|---|---|
| Line 259: | Line 259: | ||
| * What is the "Resit Assessment" | * What is the "Resit Assessment" | ||
| - Questions about contact details of Supervisors (information collected for report) | - Questions about contact details of Supervisors (information collected for report) | ||
| + | === Minute: === | ||
| + | - whenever supervisors Manuel and Fernando give "green light" on designs, work in the workshop can start | ||
| + | - a better 3D printer (higher accuracy) was arranged, Fernando will forward the drawings | ||
| + | - discussion about required shape of shaft to propel the fish, this issue will have to be experimented on the prototype | ||
| + | - a spring, installed at the last segment of the tail fin, could maybe improve the tailmovement | ||
| + | - an appointment was set with Fernando to improve little details on the parts in order to make them printable | ||
| + | - the calendar on the wiki is right, google calendar had mistakes, the upload date is on 12th June | ||
| + | - presentation can be uploaded later, one day before presentation day | ||
| + | - contact data of professionals at ISEP can be found in ISEP Portal | ||
| ==== 11th Meeting (2014-05-28) ==== | ==== 11th Meeting (2014-05-28) ==== | ||
| === Agenda: === | === Agenda: === | ||
| - Questions about list of material (concerning electrical parts) | - Questions about list of material (concerning electrical parts) | ||
| + | === Minute: === | ||
| + | - materials have not yet arrived | ||
| + | - there are problems with the procurement of battery and 3D prating wire, supervisors will take of that | ||
| + | - 3D printing can start as soon as last technical details are discussed with Fernando and implemented into the 3D model | ||
| + | - the team has to buy some of the components itself, therefore some of the budget was made available for us | ||
| + | - Video and poster can be uploaded together with presentation on 18th June | ||
| + | ==== 12th Meeting (2014-06-05) ==== | ||
| + | === Agenda: === | ||
| + | - Question about content of wiki | ||
| ==== Activities ====== | ==== Activities ====== | ||
| Line 275: | Line 292: | ||
| | 2014-03-17 | 2014-03-19 | Marketing concept | Brainstorm/ | | 2014-03-17 | 2014-03-19 | Marketing concept | Brainstorm/ | ||
| | 2014-03-20 | | product development, | | 2014-03-20 | | product development, | ||
| + | | 2014-05-12 | 2014-06-03 | Finish technical product development | prepare the 3D model so that parts can be printed, discuss details with Fernando | Marcin | | ||
| + | | 2014-05-19 | 2014-05-31 | Finish part of Project Management for Report | elaborate all issues and send file to teacher by 31th May | Magda | | ||
| + | | 2014-05-30 | 2014-06-02 | Project Management Presentation | Prepare a commercial presentation (format based on the interim assessment) | Alicia | | ||